City of Mackinac Island v. FERC No. 18-983 Opposition to a petition for a writ of certiorari seeking Supreme Court review of the D.C. Circuit decision in Verso Corp. v. FERC, 898 F.3d 1 (D.C. Cir. 2018), affirming FERC orders on refunds and surcharges of previously-allocated costs associated with the operation of System Support Resource generating units, located in the American Transmission Co. service territory, under the MISO tariff. Pub. Serv. Comm’n of Wisc. v. Midcontinent Indep. Sys. Oper., Inc., et al., order on complaint & reh’g, 148 FERC ¶ 61,071 (2014), order on reh’g & compl., 150 FERC ¶ 61,104 (2015), order on reh’g & clar., 156 FERC ¶ 61,205 (2016); order on tariff rev’ns, 152 FERC ¶ 61,216 (2015), order on reh’g & compl., 155 FERC ¶ 61,134 (2016). [Brief filed by the Solicitor General of the United States]. Circuit S. Ct.
Appellate Briefs