8th Cir. Nos. 23-1520, et al.
Orders on complaint, concerning revenue crediting process in Attachment Z2, and alleging that SPP has: (1) violated the terms of its Tariff and generator interconnection agreements; (2) engaged in unjust and unreasonable and unduly discriminatory and preferential practices; (3) violated the filed rate doctrine; and (4) violated cost causation and beneficiary pays principles. EDF Renewables, Inc., et al. v. Southwest Power Pool, Inc., 181 FERC ¶ 61,140 (2022), order on reh’g, 183 FERC ¶ 61,216 (2023); Western Farmers Elec. Coop. v. SPP, 181 FERC ¶ 61,137 (2022), order on reh’g, 183 FERC ¶ 61,218 (2023); Cimarron Windpower II, LLC v. SPP, 181 FERC ¶ 61,136 (2023), order on reh’g, 183 FERC ¶ 61,219 (2023); Oklahoma Gas and Electric Co. v. SPP, 181 FERC ¶ 61,139 (2022), order on reh’g, 183 FERC ¶ 61,217 (2023).
Appellate Briefs