People of the State of Cal., et al. v. FERC Nos. 13-71276, et al. Orders: (1) on remand from Port of Seattle, Wash. v. FERC, 499 F.3d 1016 (9th Cir. 2007), establishing an evidentiary, trial-type hearing in Pacific Northwest refund proceeding before an ALJ and addressing scope of issues (including Mobile-Sierra issues) for hearing; and (2) approving settlement between Idaho Power, IDACORP, and Powerex Corp., on the condition that settling parties remove settlement provisions precluding potential ripple claims by third-parties. Puget Sound Energy, Inc. v. All Jurisdictional Sellers of Energy and/or Capacity at Wholesale into Electric Energy and/or Capacity Markets in the Pacific Northwest, 137 FERC ¶ 61,001 (2011), order on reh’g, 143 FERC ¶ 61,020 (2013); 146 FERC ¶ 61,123 (2014), reh’g denied, 147 FERC ¶ 61,223 (2014). Circuit 9th Cir.
Appellate Briefs