3rd Cir. No. 23-1778, et al.
Order accepting PJM proposal to exclude planned generation capacity resources from the calculation of the Locational Deliverability Area Reliability Requirement if the addition of such resources materially increases the reliability requirement and such resources do not participate in the capacity auction.  PJM Interconnection, L.L.C., 182 FERC ¶ 61,109 (2023), order on reh’g, 184 FERC 61,055 (2023). 
 

This page was last updated on December 18, 2023