West Deptford Energy, LLC v. FERC No. 12-1340 Assignment of costs of already-constructed network upgrade to interconnecting generator, based on tariff language and cost allocation policy. PJM Interconnection, L.L.C., 136 FERC ¶ 61,195 (2011), reh’g denied, 139 FERC ¶ 61,184 (2012). Circuit D.C. Cir.