Date Docket No. Company Title
05/26/2015 IN14-11-000 Western Electricity Coordinating Council Order Approving Stipulation and Consent Agreement
11/28/2014 IN14-10-000 California Independent System Operator Corporation Order Approving Stipulation and Consent Agreement
11/24/2014 IN14-9-000  Western Area Power Administration – Desert Southwest Region Order Approving Stipulation and Consent Agreement
10/21/2014 IN14-8-000  Southern California Edison Company Order Approving Stipulation and Consent Agreement
08/07/2014 IN14-7-000  Imperial Irrigation District Order Approving Stipulation and Consent Agreement
07/07/2014 IN14-6-000  Arizona Public Service Company Order Approving Stipulation and Consent Agreement
01/22/2014 No docket no.  September 8, 2011 Arizona-Southern California Blackout
Arizona Public Service; California Independent System Operator; Imperial Irrigation District; Southern California Edison; Western Area Power Administration-Desert Southwest Region; Western Electricity Coordinating Council Reliability Coordinator
Staff Notice of Alleged Violations
07/10/2013 IN13-14-000  Southwest Power Pool Order Approving Stipulation and Consent Agreement
03/28/2013 IN13-9-000  Entergy Services, Inc. Order Approving Stipulation and Consent Agreement
12/14/2012 IN13-4-000  April 1, 2010 California ISO load shed event
California Independent System
Operator Corporation
Order Approving Stipulation and Consent Agreement
08/29/2011 IN11-7-000  Grand River Dam Authority Order Approving Stipulation and Consent Agreement
12/01/2011 IN11-6-000  February 14, 2008 PacifiCorp event
PacifiCorp
Order Approving Stipulation and Consent Agreement
07/07/2011 IN11-1-000  February 14, 2008 PacifiCorp event
Western Electricity Coordinating Council
Order Approving Stipulation and Consent Agreement
03/05/2010 IN08-05-000  2008 Florida Blackout
Florida Reliability Coordinating Council
Order Approving Stipulation and Consent Agreement
10/08/2009 IN08-5-000  2008 Florida Blackout
Florida Power & Light Company
Order Approving Stipulation and Consent Agreement
Date Docket No. Company Title
07/18/2013 PA12-11-000  Salt River Project Audit Letter and Report
07/10/2013 PA12-9-000  Western Electricity Coordinating Council Audit Letter and Report
06/28/2013 PA12-10-000  Northeast Power Coordinating Council Audit Letter and Report
06/11/2013 FA12-6-000  SERC Reliability Corporation Audit Letter and Report
05/09/2013 FA12-7-000  Reliability First Corporation Audit Letter and Report
05/09/2013 FA12-14-000  Midwest Reliability Organization Audit Letter and Report
04/24/2013 PA12-17-000  Bonneville Power Administration Audit Letter and Report
01/16/2013 (Settlement Order)

05/04/2012 (Report)
FA11-21-000 Settlement 

FA11-21-000 Report 
North American Electric Reliability Corporation Settlement Agreement and Audit Report
11/01/2012 PA11-21-000  PJM Interconnection, LLC Audit Letter and Report
10/29/2010 PA10-1-000  Entergy Services, Inc. Audit Letter and Report
10/05/2011 PA11-2-000  Southwest Power Pool Audit Letter and Report
08/20/2010 PA09-5-000  Western Electricity Coordinating Council Order Approving Audit Report, Determining Issue of Separation of Functions, and Directing Compliance and Other Corrective Actions
06/23/2010 PA09-7-000  Florida Reliability Coordinating Council Order Approving Audit Report, Determining Issue of Separation of Functions, and Directing Compliance and Other Corrective Actions
01/08/2010 PA09-6-000  Texas Regional Entity Order Approving Audit Report, Determining Issue of Separation of Functions, and Directing Compliance and Other Corrective Actions
01/15/2009 PA08-2-000 and AD09-3-000  Southwest Power Pool Order Approving Audit Report, Determining Issue of Separation of Functions, and Directing Compliance and Other Corrective Actions

 