Introduction
On February 17, 2026, FERC staff accepted Cheniere’s application for the Corpus Christi Liquefaction, LLC (CCL) Stage 4 Project and Cheniere Corpus Christi Pipeline, L.P. (CCPL) Expansion Project (Project) into the formal Certificate Proceeding (CP) phase under FERC’s review process. More information can be found in FERC Docket Nos. CP26-82-000, CP26-87-000, and CP18-513-000 in FERC’s eLibrary. Please note that the project has not been approved at this time.
The Commission will prepare an environmental document that will discuss the environmental impacts of the Project. The Commission will use this environmental document in its decision-making process to determine whether the Project is in public convenience and necessity.
Project Route and Facilities
The planned Project is described below according to the applicant’s filing:
CCL Stage 4 Project
The CCL Stage 4 Project will consist of the following:
- Four (4) large-scale liquefaction trains (“Trains 4-7”) with the peak production capacity of approximately 24 MTPA of LNG;
- Four (4) inlet air chilling units;
- Two (2) full-containment, aboveground, 220,000 m3 LNG storage tanks;
- One (1) marine loading jetty;
- Seven (7) boil-off-gas (“BOG”) compressors;
- One (1) new main substation;
- New operations buildings;
- One (1) marine totally enclosed ground flare;
- Three (3) multi-point ground flares; and
- New flare knockout drums and other new utilities and appurtenant facilities.
The CCL Stage 4 Project will include tie-ins to existing CCL Terminal facilities including shared utilities, LNG rundown header, elevated flares, BOG compressor(s), LNG loading lines, and an existing feed gas header.
Corpus Christi Pipeline (CCPL) Expansion Project
The CCPL Expansion Project will include new pipeline and compression facilities to increase gas delivery capacity to the CCL Terminal and the CCL Stage 4 Project by approximately 3.0 Bcf/d. The main components of the Corpus Christi Pipeline Expansion Project include:
- CCPL 42" Pipeline Loop: A new 42-inch diameter, approximately 26-mile-long pipeline from the existing Sinton Compressor Station to the CCL Stage 4 Project.
- Sinton 2 Compressor Station: Construction of a new compressor station adjacent to the existing Sinton Compressor Station.
- Interconnect Facilities: Metering and flow control infrastructure between existing and new facilities.
The CCPL Expansion Project facilities will be designed for a maximum allowable operating pressure of 1,440 pounds per square in gauge (psig) and will operate in accordance with 49 CFR Part 192 requirements. All facilities will be located entirely within San Patricio County, Texas. Associated facilities will include a pig launcher and receiver, mainline valves, and crossover valves.
Environmental Review Schedule
FERC staff will issue the Draft EIS in September 2026, opening a 45-day public comment period.
The Final EIS is expected March 12, 2027.
Federal authorization decisions are due no later than June 10, 202
More Information and Staying Updated
You may learn more about the Project through FERC’s eLibrary. When searching for the Project, please enter Docket No. P26-82-000, CP26-87-000, and CP18-513-000 in the “Enter Docket Number” text box. FERC’s Office of Public Participation provides an educational video and demonstration on using eLibrary: WorkshOPP and Demonstration: FERC’s eLibrary.
There are four (4) dockets associated with this Project:
- The Pre-Filing Docket: Docket No. PF25-10-000
- The Certificate Proceeding Docket: Docket Nos. CP26-82-000, CP26-87-000, and CP18-513-000
Stay Informed:
Follow OPP on its social media channels:
OPP regularly sends announcements about upcoming participation opportunities and meetings with interested stakeholders and organizations via its social media channels.
You may also sign up for FERC’s eSubscription service. eSubscription notifies you via email about submittals and issuances on the project. Please visit www.ferc.gov/esubscription.
You are also encouraged to contact OPP staff to learn more about the Project and participation at FERC by email at [email protected] or phone at 202-502-6595. All media inquiries should be directed to [email protected].
Resources
Guides on Public Participation
- Step-by-step guide on how to file a comment
- Step-by-step guide on how to intervene
- Step-by-step guide on how to eSubscribe
Educational Videos
- Learn to eFile, eComment, and eSubscribe
- How to File an Intervention Using FERC’s Online System
- Filing Comments Workshop and Demonstration
- Submitting Powerful Comments Workshop
Tips on Public Participation
Informational Handouts
- About FERC
- About OPP
- Natural Gas Pre-filing Open Houses: Public Participation and What to Expect
- Natural Gas Scoping Sessions: Public Participation and What to Expect
Background
- July 17, 2025: The Applicant submits request to initiate the Pre-Filing Review Process.
- August 6, 2025: FERC staff approved the Applicant’s request to enter FERC’s Pre-filing Review Process.
- September 4, 2025: The Applicant submits Preliminary Drafts Resource Report Nos. 1 and 10 for the Project.
- November 5, 2025: The Applicant submits draft Resource Report No. 13 re the CCL Stage 4 and CCPL Expansion Projects under PF25-10.
- November 5, 2025: The Applicant held an Open House for the Project.
- December 10, 2025: FERC held a Scoping Session in the potentially affected area.
- January 7, 2026: The applicant submits response to scoping comments.
- February 17, 2026: FERC staff accepted Cheniere’s application into the formal CP phase.
- March 10, 2026: FERC established a deadline for filing a motion to intervene.
- May 29, 2026: The deadline to submit comments for the draft Environmental Impact Statement
Office of Public Participation’s Outreach Corner
The Office of Public Participation (OPP) is authorized to support public participation in FERC proceedings pursuant to Section 319 of the Federal Power Act. OPP coordinates with and provides assistance to members of the public as to participation in, and understanding of, FERC proceedings. OPP provides outreach to community groups, community members, landowners and other interested parties potentially impacted by infrastructure projects.
- In Summer 2025, OPP sent an email to various regional stakeholders and community members to announce the project and open house date.
- OPP Outreach Specialist attended the Open House in the potentially affected areas in November of 2025.
- In Fall 2025, OPP sent emails and USPS mailers to various constituencies announcing the Scoping Session and comment deadline.
- OPP Outreach Specialist attended the Scoping Session in the potentially affected area in December of 2025.
- In Spring 2026, OPP sent emails and USPS mailers to various constituencies announcing the draft Environmental Impact Statement comment deadline.
How to Contact
| Company Website | Contact the Company | Landowner Communication |
|---|---|---|
|
|
Quick Links
Contact Information
-
FERC Online SupportEmail: [email protected]
-
News MediaEmail: [email protected]