Appellate Briefs

Industrial Energy Consumers, et al. v. FERC

D.C. Cir. No. 23-1334 Order authorizing ITC Midwest to recover, pursuant to Order No.
Appellate Briefs

Village of Morrisville, Vermont v. FERC

D.C. Cir. Nos. 21-1042 and 21-1109 Order denying Morrisville’s petition for a declaratory order and concluding that Vermont had not waived Clean Water Act water quality certification authority.  Village of Morrisville, Vermont, 173 FERC ¶ 61,156 (2020), order on reh’g, 174 FERC ¶ 61,141 (2021).  
Appellate Briefs

System Energy Resources, et al. v. FERC

Nos. 23-60110, et al. Order following hearing and ALJ initial decision, concerning electric plant capacity rates that are charged by System Energy Resources.  La. Pub. Serv. Comm’n v. Sys. Energy Res., Inc., Opinion No. 581, 181 FERC ¶ 61,243 (2022), order on reh’g, 184 FERC ¶ 61,097 (2023). 5th Cir.
Appellate Briefs

Stingray Pipeline Company, LLC v. FERC

D.C. Cir. No. 23-1288 Order authorizing abandonments, of offshore and mainline facilities, by removal, in-place, and sale to Triton Gathering LLC, and determining jurisdictional status of facilities.  Stingray Pipeline Co., L.L.C., 183 FERC ¶ 61,201 (2023), order on reh’g, 185 FERC ¶ 61,171 (2023).
Appellate Briefs

Capital Power Corporation, et al. v. FERC

D.C. Cir. No. 23-1134, et al. Order on tariff revisions concerning reactive power supply. Midcontinent Independent System Operator, Inc., 182 FERC ¶ 61,033 (2023), order on reh’g, 184 FERC ¶ 61,022 (2023).  
Appellate Briefs

Public Utilities Commission of Ohio v. FERC, et al.

S. Ct. No. 23-1069 Brief for the Federal Energy Regulatory Commission.  PJM proposed revisions to its Open Access Transmission Tariff, regarding application of the Minimum Offer Price Rule in its capacity market, go into effect by operation of law.  PJM Interconnection, L.L.C., Notice of Filing Taking Effect by Operation of Law (Sept. 29, 2021) (noting that Commission did not act on PJM’s filing “because the Commissioners are divided two against two as to the lawfulness of the change”), rehearing denied by operation of law, 177 FERC ¶ 62,105 (Nov. 29, 2021).  
Appellate Briefs

Entergy Arkansas, LLC, et al. v. FERC

D.C. Cir. No. 22-1334 and 23-1151 Order rejecting proposed tariff revisions, to require market participants representing load serving entities participating in MISO’s planning resource auction to implement a Minimum Capacity Obligation.  Midcontinent Independent System Operator,  Inc., 180 FERC ¶ 61,142 (2022), order on reh’g, 183 FERC  ¶ 61,112 (2023).
Appellate Briefs

Kimball Wind, LLC v. FERC

D.C. Cir. No. 23-1236 Order denying complaint and petition, seeking reimbursement of funds paid to WAPA for the expansion of WAPA’s Kimball Substation.  Kimball Wind, LLC v. Western Area Power Administration, Rocky Mountain Region, 183 FERC ¶ 61,085 (2023), order on reh’g, 184 FERC ¶ 61,150 (2023).
Appellate Briefs

Electric Power Supply Association v. FERC

S. Ct. No. 23-773 Brief for the Federal Respondent in Opposition. Order adopting the PJM Market Monitor’s Unit-Specific Avoidable Cost Rate, and granting PJM request for waiver of certain pre-auction deadlines in the event the Commission establishes a lower value for the replacement default offer cap.  Independent Market Monitor for PJM v. PJM Interconnection, L.L.C., 176 FERC ¶ 61,137 (Sept. 2, 2021); Notice of denial of rehearing by operation of law and providing for further consideration, 177 FERC ¶ 62,066 (Nov. 4, 2021); Order on Rehearing, 178 FERC ¶ 61,121 (Feb. 18, 2022).
Appellate Briefs

Healthy Gulf, et al.

D.C. Cir. No. 23-1226 Order issuing certificate to construct and operate two new interstate natural gas pipelines (Line 200 and Line 300 Project) in Beauregard and Calcasieu Parishes, Louisiana.  Driftwood Pipeline LLC, 183 FERC ¶ 61,049 (2023); Notice of Denial of Rehearing by Operation of Law, 185 FERC ¶ 62,064 (Nov. 6, 2023).
Appellate Briefs

City of Port Isabel, et al. v. FERC

D.C. Cir. No. 23-1175, et al. Order on remand, reaffirming authorization of Texas LNG facility. Texas LNG Brownsville LLC, 183 FERC ¶ 61,047 (2023), order on reh’g, 185 FERC ¶ 61,079 (2023).
Appellate Briefs

City of Port Isabel, et al. v. FERC

D.C. Cir. No. 23-1174, et al. Order on remand from 2021 D.C. Cir. decision, Vecinos para el Bienestar de la Comunidad Costera v. FERC, 6 F.4th 1321 (D.C. Cir. 2021), and amending Rio Grande LNG certificate.  Rio Grande LNG, LLC & Rio Bravo Pipeline Company, LLC, 183 FERC ¶ 61,046 (2023), order on reh’g, 185 FERC ¶ 61,080 (2023).
Appellate Briefs

In re: Louisiana Public Service Commission

5th Cir. No. 60113 Response of Federal Energy Regulatory Commission in Opposition to Renewed Petition For Writ of Mandamus
Appellate Briefs

Tenaska Clear Creek Wind, LLC v. FERC

D.C. Cir. No. 23-1081 and 23-1152 Order denying complaint and petition, alleging that SPP and AECI have adopted certain operating guides that result in improper curtailment of Tenaska’s Clear Creek Wind generating facility.  Tenaska Clear Creek Wind, LLC v. Southwest Power Pool, Inc., et al., 181 FERC ¶ 61,1225 (2022), order on reh’g, 183 FERC ¶ 61,043 (2023).
Appellate Briefs

Hecate Energy LLC v. FERC

D.C. Cir. No. 23-1089, et al. Order conditionally accepting filing to reform PJM interconnection process, by transitioning from a serial first-come, first-served queue process to a first-ready, first-served clustered cycle approach.  PJM Interconnection, L.L.C., 181 FERC ¶ 61,162 (2022), order on reh’g, 184 FERC ¶ 61,006 (2023).    
Appellate Briefs

Central Hudson Gas & Electric Corporation, et al. v. FERC

D.C. Cir. No. 21-1256, et al. Orders rejecting rate filing and denying complaint, challenging funding methodology for System Upgrade Facilities and System Deliverability Upgrades.  New York Independent System Operator, Inc., et al., 176 FERC ¶ 61,143 (2021), and Central Hudson Gas & Electric Corp., et al. v. New York Independent System Operator, Inc., 176 FERC ¶ 61,149 (2021), order on reh’g, 178 FERC ¶ 61,194 (2022).  
Appellate Briefs

Citizens Action Coalition of Indiana, Inc. v. FERC

D.C. Cir. No. 23-1046 Order granting, subject to conditions, Texas Gas application to construct and operate natural gas facilities in Kentucky and Indiana (Henderson County Expansion Project), to serve new natural gas-fired electric generation turbines at CenterPoint’s existing A.B. Brown plant in Posey County, Indiana.  Texas Gas Transmission, LLC, 181 FERC ¶ 61,049 (2022); Notice of Denial of Rehearing by Operation of Law and Providing for Further Consideration, 181 FERC ¶ 62,197 (Dec. 22, 2022); Notice of Denial of Rehearing by Operation of Law (June 8, 2023).  
Appellate Briefs

Appalachian Power Company v. FERC

4th Cir. No. 23-1192 Order on petition for declaratory order, asking the Commission to declare that Blue Ridge members are permitted to utilize battery storage technology on their systems to manage their demands under the terms of full requirements power contracts with Appalachian Power.  Blue Ridge Power Agency, 181 FERC ¶ 61,048 (2022); Notices of Denial of Rehearing by Operation of Law, 181 FERC ¶ 62,199 (2022) and 184 FERC ¶ 62,048 (2023).  
Appellate Briefs

City of Port Isabel, et al. v. FERC

D.C. Cir. No. 23-1174, et al. Respondent’s opposition to motion for stay. Rio Grande LNG, LLC & Rio Bravo Pipeline Company, LLC, 183 FERC ¶ 61,046 (2023), order on reh’g, 185 FERC ¶ 61,080 (2023).   
Appellate Briefs

Pacific Gas and Electric Company v. FERC

D.C. Cir. No. 23-1041, et al. Order on remand, concluding that San Francisco’s loads within the customer classes served on October 24, 1992, are entitled to grandfathered service under PG&E’s Wholesale Distribution Tariff.  City & Cty. of San Francisco v. Pac. Gas & Elec. Co., 181 FERC ¶ 61,036 (2022), order on reh’g, 182 FERC ¶ 61,167 (2023).