Docket No. CP22-461-001

I dissent from Paragraph 10 of the Order,[1] which is the so-called “Driftwood compromise” language claiming that the Commission is incapable of assessing the significance of greenhouse gas (GHG) emissions.   

 In my concurrence in the Certificate Order, I explained the history of this language.[2]  In Driftwood, the majority suddenly declared that there are no methods for assessing the significance of GHG emissions, and particularly criticized the Social Cost of GHGs protocol.[3]  I have dissented from this language in Driftwood and subsequent orders because (1) it reflects a final Commission decision that it cannot determine the significance of GHG emissions, despite the fact the Commission has never responded to comments in the GHG Policy Statement docket[4] addressing methods for doing so; and (2) the language departs from previous Commission precedent without reasoned explanation, thereby violating the Administrative Procedure Act.[5]  I dissent from Paragraph 10 of this Order for the same reasons.

As I have said before, the Commission has not seriously studied whether the Social Cost of GHGs protocol or another tool can or should be used to determine significance.  Rather, the majority simply decided there is no acceptable method, with no explanation of why the Commission departed from the approach taken in earlier certificate orders.[6]  I cannot condone the Commission’s refusal to objectively consider potential methods for assessing the impacts of GHG emissions and transparently incorporate GHG impacts in its determination of the public convenience and necessity under the Natural Gas Act.

For these reasons, I respectfully dissent in part.

 


[2] See Transcon. Gas Pipe Line Co., 184 FERC ¶ 61,066 (2023) (Clements, Comm’r, concurring at PP 2-3) (Certificate Order).

[3] See Driftwood Pipeline LLC, 183 FERC ¶ 61,049, at PP 61, 63 (2023) (Driftwood).

[4] Docket No. PL21-3.

[5] See Driftwood, 183 FERC ¶ 61,049 (Clements, Comm’r, dissenting at PP 2-3 & n.161); see also Columbia Gas Transmission, LLC, 186 FERC ¶ 61,048 (2024) (Clements, Comm’r, dissenting in part at PP 3-4); Transcon. Gas Pipe Line Co., 186 FERC ¶ 61,047 (2024) (Clements, Comm’r, dissenting at PP 8-9); Tennessee Gas Pipeline Co., L.L.C., 186 FERC ¶ 61,046 (2024) (Clements, Comm’r, dissenting in part at PP 1-2); ANR Pipeline Co., 185 FERC ¶ 61,191 (2023) (Clements, Comm’r, dissenting in part at PP 2-3); Transcon. Gas Pipe Line Co., 185 FERC ¶ 61,133 (2023) (Clements, Comm’r, dissenting in part at PP 35, 44); Transcon. Gas Pipe Line Co., 185 FERC ¶ 61,130 (2023) (Clements, Comm’r, dissenting in part at PP 100-101); Texas LNG Brownsville LLC, 185 FERC ¶ 61,079 (2023) (Clements, Comm’r, dissenting at PP 9-10); Rio Grande LNG, LLC, 185 FERC ¶ 61,080 (2023) (Clements, Comm’r, dissenting at PP 9-10); Gas Transmission Northwest, LLC, 185 FERC ¶ 61,035 (2023) (Clements, Comm’r, concurring in part and dissenting in part at PP 7-8); WBI Energy Transmission, Inc., 185 FERC ¶ 61,036 (2023) (Clements, Comm’r, dissenting in part at PP 2-3); Venture Global Plaquemines LNG, LLC, 185 FERC ¶ 61,037 (2023) (Clements, Comm’r, dissenting in part at PP 2-3); Texas Eastern Transmission, LP, 185 FERC ¶ 61,038 (2023) (Clements, Comm’r, dissenting in part at PP 2-3); Trailblazer Pipeline Company LLC, 185 FERC ¶ 61,039 (2023) (Clements, Comm’r, dissenting in part at PP 2-4); Equitrans, L.P., 185 FERC ¶ 61,040 (2023) (Clements, Comm’r, dissenting in part at PP 2-4); Port Arthur LNG Phase II, LLC, 184 FERC ¶ 61,184 (2023) (Clements, Comm’r, dissenting in part at PP 2-3); Venture Global Calcasieu Pass, LLC, 184 FERC ¶ 61,185 (2023) (Clements, Comm’r, dissenting in part at PP 2-4); Northern Natural Gas Company, 184 FERC ¶ 61,186 (2023) (Clements, Comm’r, dissenting in part at PP 2-3); Texas Eastern Transmission, LP, 184 FERC ¶ 61,187 (2023) (Clements, Comm’r, dissenting in part at PP 2-4); Equitrans, L.P., 183 FERC ¶ 61,200 (2023) (Clements, Comm’r dissenting at PP 2-3); Commonwealth LNG, LLC, 183 FERC ¶ 61,173 (2023) (Clements, Comm’r, dissenting at PP 5-8); Rio Grande LNG, LLC, 183 FERC ¶ 61,046 (2023) (Clements, Comm’r, dissenting at PP 14-15); Texas LNG Brownsville LLC, 183 FERC ¶ 61,047 (2023) (Clements, Comm’r, dissenting at PP 14-15).

[6] Before its decision in Driftwood, the Commission had explained that it was not determining the significance of GHG emissions because the issue of how to do so was under consideration in the GHG Policy Statement docket.  See, e.g., Transcon. Gas Pipe Line Co., 182 FERC ¶ 61,006, at P 73 & n.174 (2023); Columbia Gas Transmission, LLC, 182 FERC ¶ 61,171, at P 46 & n.93 (2023).  To depart from prior precedent without explanation violates the Administrative Procedure Act.  See, e.g., West Deptford Energy, LLC v. FERC, 766 F.3d 10, 17 (D.C. Cir. 2014) (“[T]he Commission cannot depart from [prior] rulings without providing a reasoned analysis. . . .”) (citations omitted).

 

Contact Information