No. 19-72886 and 72925 (9th Cir. filed 11/14/2019)Allegations that PGE and SoCal Edison violated Order 890 obligation to conduct an open, coordinated, and transparent transmission planning process, by failing to allow stakeholder input and review. Cal. Pub. Utils. Commn, et al. v. Pac. Gas Elec. Co., 164 FERC ¶61,161 (2018), reh'g denied, 168 FERC ¶ 61,171 (2019); and S. Cal. Edison Co., 164 FERC ¶61,160 (2018), reh'g denied, 168 FERC ¶ 61,170 (2019).et al.

This page was last updated on October 05, 2020