D.C. Cir. No. 23-1040
Order affirming ALJ’s initial decision, that accepted MISO filings to: (1) include Henderson Municipal Power and Light as a transmission owner in MISO’s Rate Zone 27 (the Big Rivers pricing zone); and (2) allow Henderson to recover its portion of its revenue requirement related to certain transmission facilities located in that pricing zone.  Midcontinent Independent System Operator, Inc., Opinion No. 580, 181 FERC ¶ 61,056 (2022), order on reh’g, 182 FERC ¶ 61,095 (2023).
 

This page was last updated on December 18, 2023