El Paso Electric Co. v. FERC No. 14-60822 Filing, by members of WestConnect, in compliance with transmission planning and cost allocation requirements of Order No. 1000, requesting that regional cost allocation be categorically inapplicable to any project providing benefits to a transmission owner not enrolled in the WestConnect region – including public power utilities. Public Service Co. of Colorado, et al., 142 FERC ¶ 61,206 (2013), order on reh’g & compl., 148 FERC ¶ 61,213 (2014), order on reh’g & compl., 151 FERC ¶ 61,128 (2015). Circuit 5th Cir.