No. 19-1074 (D.C. Cir. filed 4/2/2019)

Certificate to construct and operate Westlake Expansion Project in Louisiana; denial of proposed rate design (proposed separate incremental recourse reservation rate and usage rate for service on the Project).  Gulf South Pipeline Co., LP, 163 FERC ¶ 61,124 (2018), reh’g denied, 166 FERC ¶ 61,089 (2019).
 

Status Update

  1. Status:  petition for review granted in part and the portion of FERC's order rejecting incremental-plus rates be vacated. The petition for review denied in all other respects, and case remanded to FERC for further proceeding on 4/10/2020

This page was last updated on May 13, 2020