Map of the Central region for triennial review.

The Commission will review each region every three years according to a rotating schedule. The Central region, which is made up of MISO and NERC Region MRO and RFC (not including PJM) will be reviewed on the following dates, and every three years thereafter, depending on what type of entity the seller is.


Central Schedule for Filing from Order 697-A
Study Period Filing Period Entities Required to File
December 1, 2012 - November 30, 2013 December, 2014 Transmission Owning Utilities
December 1, 2012 - November 30, 2013 June, 2015 Non-Transmission Owning Utilities
December 1, 2015 - November 30, 2016 December, 2017 Transmission Owning Utilities
December 1, 2015 - November 30, 2016 June, 2018 Non-Transmission Owning Utilities
December 1, 2018 - November 30, 2019 December, 2020 Transmission Owning Utilities
December 1, 2018 - November 30, 2019 June, 2021 Non-Transmission Owning Utilities
December 1, 2021 - November 30, 2022 December, 2023 Transmission Owning Utilities
December 1, 2021- November 30, 2022 June, 2024 Non-Transmission Owning Utilities

Back to When and What to File  