Map of the Southeast Region for triennial review.

The Commission will review each region every three years according to a rotating schedule. The Southeast, which is made up of NERC Regions SERC and FRCC (not including PJM or MISO) will be reviewed on the following dates, and every three years thereafter, depending on what type of entity the seller is.


Southeast Schedule for Filing from Order 697-A
Study Period Filing Period Entities Required to File
December 1, 2011 - November 30, 2012 June, 2014 Transmission Owning Utilities
December 1, 2011 - November 30, 2012 December, 2014 Non-Transmission Owning Utilities
December 1, 2014 - November 30, 2015 June, 2017 Transmission Owning Utilities
December 1, 2014 - November 30, 2015 December, 2017 Non-Transmission Owning Utilities
December 1, 2017 - November 30, 2018 June, 2020 Transmission Owning Utilities
December 1, 2017 - November 30, 2018 December, 2020 Non-Transmission Owning Utilities
December 1, 2020 - November 30, 2021 June, 2023 Transmission Owning Utilities
December 1, 2020- November 30, 2021 December, 2023 Non-Transmission Owning Utilities

Back to When and What to File  

This page was last updated on June 17, 2020