Docket No. ER12-2708-010, et al.

An uncontested final settlement of a rate case dating back nearly a decade and a half may seem hardly noteworthy.  But as Willy Loman’s wife Linda said in Death of a Salesman, “attention must be paid;”[1] paid to the PATH example, that is, because of the major lessons – and warnings – it holds for long-term regional transmission planning driven by policy goals, the substantial costs that go with such projects, and how FERC’s policies inflate those costs to consumers. 

First the basic facts:  The PATH project was planned as a long-distance, high-voltage transmission line crossing three states that was approved for construction and regional cost allocation through selection for PJM’s regional transmission expansion plan (RTEP).[2]  PATH applied for certificates of public need in three states – West Virginia, Virginia, and Maryland – none of which ever issued a certificate.  PJM later removed PATH from the RTEP, and it was never built.

Even though not a single ounce of steel was ever put in the ground, PATH’s developers have been collecting money from retail customers in the PJM states ever since it was approved for PJM’s RTEP.  Since 2008, the total amount that consumers have been forced to pay to PATH’s developers has been approximately $250 million – that’s right, let me repeat:  consumers have paid roughly $250 million for a project that was never built nor found needed by a single state regulator.  Adding insult to consumers’ injury, that amount was caused and inflated by a whole host of Commission-approved transmission incentives:

Approval of a 50-basis point incentive return on equity (ROE) adder to PATH’s base ROE for becoming a member of PJM (RTO participation adder);

  • Approval of a 150-basis point incentive ROE adder to PATH’s base ROE for the risks and challenges related to the PATH project;
  • Authorization to include 100% of Construction Work in Progress in rate base (CWIP Incentive);
  • Permission to file for recovery of development and construction costs if the project is abandoned for reasons beyond PATH’s control (Abandoned Plant Incentive);
  • Permission to use a hypothetical capital structure of 50 percent debt and 50 percent equity during the construction period (Hypothetical Capital Structure Incentive);
  • Authorization to include in rate base an unamortized regulatory asset, consisting of deferred pre-commercial expenses not included in CWIP, and to amortize the deferred amounts during the construction period; and
  • Authorization to apply and accrue carrying charges on the regulatory asset using an Allowance for Funds Used During Construction rate until the deferred amounts are included in rate base.[3]

By this point, you may be asking yourself whether there are any incentives the Commission did not give to the PATH developers.

So this order, which appears to be a routine uncontested settlement – a “nothing-burger” – is actually a very big deal in terms of the important lessons it teaches: 

First, the Commission’s incentives policies for years have been ridiculously generous to transmission developers while inflicting an ongoing victimization of consumers.  I have repeatedly criticized these incentives – particularly the CWIP Incentive, Abandoned Plant Incentive, and RTO participation adder – in numerous cases since I joined the Commission.[4]

Second, the Commission’s formula rate structure – which confers a presumption of prudence to transmission developers when they file for cost recovery – facilitated this assault on consumers, as it does regularly.  As I have done with incentives, I have frequently spoken out on the need to reform and revise those formula rate processes.[5]  This case illustrates exactly why.

Finally, PATH graphically illustrates the inherent dangers in approving for regional cost allocation long-distance projects based on a prediction (i.e., a guess) of what the generation mix will be in 20 years or more.  PATH was originally part of the huge “Project Mountaineer” scheme – announced with great fanfare right here at the Commission itself – to build three high-voltage lines across hundreds of miles from West Virginia to East Coast load centers.[6]  The vast majority of the power to be delivered along these lines was to be coal-generated.  After running into a firestorm of opposition in both the states in the path (no pun intended), as well as the end-user load states, Project Mountaineer was abandoned except for the PATH project, which represented a segment of one of the proposed Project Mountaineer lines.[7]  That segment was never built either.  Yet, consumers have been paying for it ever since.  The lesson here is clear:  For policy-driven long-distance, regional transmission projects affecting consumers in multiple states, it is absolutely essential that state regulators have the authority to approve – or disapprove – the construction of these lines and how they are selected for regional cost allocation and what that cost allocation formula is, if their consumers are going to be hit with the costs. 

As the Commission considers reforms to its transmission incentives policy,[8] transmission planning and cost management,[9] and its regional transmission planning and cost allocation requirements,[10] “attention must be paid” to these lessons.

For these reasons, I respectfully concur.

 

[1] Arthur Miller, Death of a Salesman, Act 1 (1949) (emphasis added).

[2] PATH was organized as a joint venture between American Electric Power Company, Inc. (AEP) and Allegheny Energy, Inc. (Allegheny) in 2007.  Allegheny merged with FirstEnergy Corp. (FirstEnergy) on February 25, 2011, and FirstEnergy became the ultimate upstream owner of Allegheny’s interests in the PATH project at that time.  E.g., PJM Interconnection, LLC, 141 FERC ¶ 61,177, at P 2 & n.2 (2012), reh’g denied, 153 FERC ¶ 61,308 (2015).

[3] See, e.g., Potomac-Appalachian Transmission Highline, L.L.C., 122 FERC ¶ 61,188, at PP 28, 40, 45, 52, 54-55, 104 (2008), order on reh’g and settlement agreement, 133 FERC ¶ 61,152, at PP 69, 82 & n.122 (2010).

[4] See, e.g., The Potomac Edison Co., 185 FERC ¶ 61,083 (2023) (Christie, Comm’r, concurring at P 2), https://www.ferc.gov/news-events/news/commissioner-christies-concurrence-concerning-potomac-edisons-abandoned-plant; Montana-Dakota Utils. Co., 185 FERC ¶ 61,015 (2023) (Christie, Comm’r, concurring at P 2), https://www.ferc.gov/news-events/news/commissioner-christies-concurrence-montana-dakota-utilities-co-regarding; Midcontinent Indep. Sys. Operator, Inc., 184 FERC ¶ 61,136 (2023) (Christie, Comm’r, concurring at P 2), https://www.ferc.gov/news-events/news/commissioner-christies-concurrence-midcontinent-independent-system-operator-inc-0; GridLiance W. LLC, 184 FERC ¶ 61,129 (2023) (Christie, Comm’r, concurring at P 2), https://www.ferc.gov/news-events/news/commissioner-christies-concurrence-gridliance-west-regarding-transmission; Midcontinent Indep. Sys. Operator, Inc., 184 FERC ¶ 61,034 (2023) (Christie, Comm’r, dissenting at P 2), https://www.ferc.gov/news-events/news/commissioner-christies-dissent-award-transmission-incentives-nipsco-er23-1904; Otter Tail Power Co., 183 FERC ¶ 61,121 (2023) (Christie, Comm’r, concurring at P 2), https://www.ferc.gov/news-events/news/e-18-commissioner-christies-concurrence-otter-tail-power-company-regarding; LS Power Grid Cal., LLC, 182 FERC ¶ 61,201 (2023) (Christie, Comm’r, concurring at P 2), https://www.ferc.gov/news-events/news/commissioner-christies-concurrence-ls-power-grid-regarding-transmission-incentives; Nev. Power Co., 182 FERC ¶ 61,186 (2023) (Christie, Comm’r, concurring at P 2), https://www.ferc.gov/news-events/news/commissioner-christies-concurrence-nv-energy-regarding-transmission-incentives; The Dayton Power and Light Co., 182 FERC ¶ 61,147 (2023) (Christie, Comm’r, concurring at P 2), https://www.ferc.gov/news-events/news/commissioner-christies-concurrence-dayton-power-and-light-company-regarding; Midcontinent Indep. Sys. Operator, Inc., 182 FERC ¶ 61,039 (2023) (Christie, Comm’r, concurring at P 2), https://www.ferc.gov/news-events/news/commissioner-christies-concurrence-midcontinent-independent-system-operator-inc; NextEra Energy Transmission Sw., LLC, 180 FERC ¶ 61,032 (2022) (Christie, Comm’r, concurring at P 2) (July 2022 Concurrence), https://www.ferc.gov/news-events/news/commissioner-christies-concurrence-nextera-energy-transmission-southwest-llc; NextEra Energy Transmission Sw., LLC, 178 FERC ¶ 61,082 (2022) (Christie, Comm’r, concurring at P 2) (February 2022 Concurrence), https://www.ferc.gov/news-events/news/commissioner-mark-c-christie-concurrence-nextera-energy-transmission-southwest-llcSee also DCR Transmission, L.L.C., 184 FERC ¶ 61,199 (2023) (Christie, Comm’r, concurring at P 6), https://www.ferc.gov/news-events/news/commissioner-christies-concurrence-dcr-transmission-regarding-transmission-cost.

[5] See, e.g., Sw. Power Pool, Inc., 183 FERC ¶ 61,151 (2023) (Clements, Comm’r, and Christie, Comm’r, concurring at P 4) (“Indeed, the Commission grants formula rate treatment, including a presumption of prudence, to filings from transmission owners seeking cost recovery for transmission projects without regard to whether such projects have been subject to a serious vetting in any proceeding in which both need and prudence of cost must be demonstrated by the transmission developer.  We have expressed concerns about this lack of oversight previously, and this filing by SPP illustrates exactly why that is a major problem pertinent to the issue of rising consumer costs for transmission.”), https://www.ferc.gov/news-events/news/commissioner-clements-and-commissioner-christies-joint-concurrence-spp-project; Transmission Planning and Cost Management, Technical Conference, Docket No. AD22-8-000, Tr. 16:4-20:11 (Comm’r Mark Christie) (Oct. 6, 2022), https://www.ferc.gov/media/transcript-docket-no-ad22-8-000.

[6] See Steve Huntoon, The Rise and Fall of Big Transmission, fortnightly magazine, September 2015, https://www.fortnightly.com/fortnightly/2015/09/rise-and-fall-big-transmission.

[7] Id.

[8] See Elec. Transmission Incentives Policy Under Section 219 of the Fed. Power Act, Supplemental Notice of Proposed Rulemaking, 175 FERC ¶ 61,035 (2021).

[9] See Transmission Plan. & Cost Management; Joint Fed.-State Task Force on Elec. Transmission, Notice Inviting Post-Technical Conference Comments, Docket Nos. AD22-8-000 and AD21-15-000 (Dec. 23, 2022).

[10] See Bldg. for the Future Through Elec. Reg’l Transmission Plan. & Cost Allocation & Generator Interconnection, Notice of Proposed Rulemaking, 179 FERC ¶ 61,028 (2022).

Contact Information


This page was last updated on December 19, 2023