MW ISO Transmission Owners, et al. v. FERC Nos. 02-1121, et al. Decision that the Midwest ISO Schedule 10 cost adder should include in its calculation all loads (including bundled retail and grandfathered wholesale load) using the regional grid that the ISO operates. Midwest Independent Transmission System Operator, Inc., et al., 97 FERC ¶ 61,033 (2001), order on reh'q, 98 FERC ¶ 61,141 (2002), order on voluntary remand, 102 FERC 61,192 (2003), reh'g denied, 104 FERC 61,012 (2003). Circuit D.C. Cir.

This page was last updated on August 06, 2020