Southern California Edison Co. v. FERC Nos. 11-1471 Order approving a base return on equity of 9.54 percent for Southern California Edison’s transmission projects; selection of median rather than midpoint within zone of reasonableness. Southern California Edison Co., 131 FERC ¶ 61,020 (2010), order on reh’g and clar., 137 FERC ¶ 61,016 (2011). Circuit D.C. Cir.

This page was last updated on August 07, 2020