Town of Norwood, Massachusetts v. FERC Nos. 06-1658, et al. Calculation of Contract Termination Charge payable by Norwood to terminate early full requirements contract with New England Power Co. Town of Norwood, Mass. v. National Grid USA, et al., 112 FERC ¶ 61,099 (2005), order on reh'g, 114 FERC ¶ 61,187 (2006), reh'g and stay denied, 115 FERC ¶ 61,396 (2006). Circuit 1st Cir.
Appellate Briefs