Commissioner James Danly Statement
December 3, 2021

Docket No. CP17-40-007

I concur in today’s order issuing a temporary certificate to Spire STL Pipeline LLC (Spire) to allow it to continue operating while the Commission considers what action to take on remand.[1]  Having recently discovered the Fifth Circuit case, Hunt Oil Company v. FPC,[2] I now conclude that the case law interpreting the scope of the Commission’s authority is not as one-sided as I had earlier thought it to be.[3]  Since the Commission’s action here constitutes at least a plausible exercise of our authority, is not explicitly prohibited, and Spire’s shipper Spire Missouri Inc. (Spire Missouri) is, from the record now in hand, evidently in dire need of service, I support the issuance of a temporary certificate. 

While I concur with the issuance of a certificate under section 7(c), I dissent insofar as the Commission has again[4] refused to address whether section 7(h) of the Natural Gas Act (NGA) confers eminent domain authority upon temporary certificate holders.[5]  It is a complicated question.  The Commission should announce its view on the matter in the first instance.

While pleased that the Commission has authorized Spire to continue service, I remain troubled by how this entire proceeding has been handled.  Although undoubtedly challenging, the Commission’s prosecution of this matter has suffered a number of self-inflicted wounds.  The first of which was the Chairman’s decision not to seek rehearing of the court’s vacatur of Spire’s certificate, a decision taken in the face of a majority of the Commission deciding otherwise.[6] 

The unforced errors continued with the Chairman’s unprecedented decision to notice Spire’s request for a temporary emergency certificate for a 60-day comment period ending October 5, 2021,[7] despite Spire noting the court’s mandate could be issued as soon as August 13, 2021.[8]  It is not typical Commission practice to establish such a long comment period; they are almost invariably set at 21 days.[9]

The Chairman then allowed unnecessary urgency to build by directing FERC’s lawyers to neither seek delay of the issuance of the court’s mandate nor to support Spire’s request to do so.  Though true that the “legal dream team”[10] failed to persuade the court to reconsider its ruling, nothing could have been lost by the Commission making such a request.  And knowing that nothing could have been lost by asking for a stay or by supporting Spire’s request for one, I can only imagine how the silence of the Commission (the agency charged with ensuring the continuity of service) was perceived.

The Commission then further complicated matters by issuing a temporary emergency certificate sua sponte to avoid a potential cessation of service to Spire Missouri and to buy time to “complete its assessment of the validity of [Spire’s] claims and determine an appropriate course of action.”[11]  Not only did this order allow the Commission to (temporarily) rescue the people of St. Louis from a trap that the Commission itself laid down, but it was logically unjustifiable.  When reduced to its essence, the order amounted to a finding that there would be an emergency while at the same time explicitly reserving to the Commission the right to determine at a later date whether, in fact, there would be an emergency.  Worst of all, the Commission—who issued this order sua sponte and could establish its contents according to its whim—set the temporary emergency certificate to expire in the middle of winter, on December 13, 2021, ginning up the artificial urgency leading to today’s issuance.

The most recent failure came again today with the Commission’s second refusal to interpret whether temporary emergency certificates holders are entitled to exercise eminent domain authority under NGA section 7(h).  As I stated before, “[t]o require the parties to go to court in order to learn whether NGA section 7(h) confers eminent domain authority upon temporary certificate holders is irresponsible and unnecessary.”[12]

The impacts of this mismanagement should not be minimized.  First responders and the public in St. Louis expended significant resources to prepare for a potential state of emergency (loss of service from Spire starting December 13, 2021), despite there being “many more pressing issues that require[d] [their] time, attention, and money.”[13]  Likewise, Spire Missouri prepared for a potential emergency by “investigating and acquiring alternative sources of supply.”[14]  Spire Missouri stated it may “spend $5 million or more in preparation for the upcoming winter heating season without STL Pipeline service. . . .  Spire Missouri will likely need to decide whether to incur these incremental costs in October, which would be unnecessary in the absence of uncertainty regarding Spire STL service . . . .”[15]  It is now December.  In addition, it is likely that commercial and industrial customers prudently hedged their positions by acquiring alternative sources of natural gas to ensure that they would be able to meet their contractual requirements.

Some may argue that these expenditures were unnecessary as it was unlikely that the Commission would allow St. Louis to lose natural gas service for the winter.  That may be true.  However, when one has a duty to serve the public or an obligation to fulfill the terms of a contract, one cannot simply rely on likelihoods.  This is especially true here, given the extraordinarily unusual treatment of Spire’s request,[16] the Commission’s surprise issuances,[17] and the fact that neither the Commission nor any commissioner (to my knowledge) committed to act before the December 13 expiration until November 18, 2021.[18]

For these reasons, I respectfully concur in part and dissent in part.

 

 

[1] Spire STL Pipeline LLC, 177 FERC ¶ 61,147 (2021) (December 2021 Order).

[2] 334 F.2d 474, 480 (5th Cir. 1964) (“There is no indication that, at the time the temporary certificates were issued, the emergency no longer existed.  In fact, at that time, the emergency had become bilateral.  Consumers were then dependent on the supplies of gas provided pursuant to the original certificates.  Under the circumstances, the Commission was authorized by [section] 7(c) of the Act to issue temporary authorization ‘in cases of emergency, to assure maintenance of adequate service or to serve particular customers, without notice or hearing, pending the determination of (the) application for a certificate.’”).

[3] See Spire STL Pipeline LLC, 176 FERC ¶ 61,160 (Danly, Comm’r, dissenting at PP 2-4) (September 2021 Order).

[4] Spire STL Pipeline LLC, 177 FERC ¶ 61,114 (2021) (Danly, Comm’r, dissenting at PP 7-17).

[5] December 2021 Order, 177 FERC ¶ 61,147 at P 70.

[6] See September 2021 Order, 176 FERC ¶ 61,160 (Danly, Comm’r, dissenting at P 9 & n.17). 

[7] See September 2021 Order, 176 FERC ¶ 61,160 (Danly, Comm’r, dissenting at P 7 n.11).

[8] Spire STL Pipeline LLC July 26, 2021 Application, Docket No. CP17-40-007, at 3 n.9.

[9] Standard practice is to notice a certificate application for a 21-day comment and intervention period.  See, e.g., Commission Staff September 7, 2021 Notice of Applications and Establishing Intervention Deadline in ANR Pipeline Company Docket No. CP21-488-000 (21-day comment and intervention deadline); Commission Staff September 1, 2021 Notice of Amendment to Application and Establishing Intervention Deadline in Roaring Fork Interstate Gas Transmission, LLC Docket No. CP21-462-000 (21-day comment and intervention deadline); Commission Staff August 26, 2021 Notice of Application Establishing Intervention Deadline in Diversified Midstream, LLC Docket No. CP21-484-000 (21-day comment and intervention deadline); Commission Staff August 26, 2021 Notice of Petition for Declaratory Order in Northern States Power Company Docket No. CP21-486-000 (21-day comment and intervention deadline); Commission Staff August 2, 2021 Notice of Applications and Establishing Intervention Deadline in Rover Pipeline, LLC Docket No. CP21-474-000 (21-day comment and intervention deadline). 

[10] Tom Tiernan, Glick disputes Danly, defends tweak to FERC litigation policy, The Energy Daily, Oct. 26, 2021.

[11] September 2021 Order, 176 FERC ¶ 61,160 at P 8.

[12] Spire STL Pipeline LLC, 177 FERC ¶ 61,114 (2021) (Danly, Comm’r, dissenting at 8).  See also Carolyn Elefant on behalf of landowners along the Spire STL Pipeline November 24, 2021, Docket No. CP17-40-004, Comments at 2 (“If these issues are not resolved, the landowners will be forced to invest even more time and money to seek appeal of court decisions such as the one attached . . .  Although courts have played fast and easy with landowners’ property rights under the Natural Gas Act, there is no precedent that would allow a company to take rights in perpetuity under a temporary certificated intended to operate as a short-term, backstop measure to avoid disruption that would otherwise flow from the invalidated authorization.”).

[13] Missouri Police Chief Association Oct. 28, 2021, Docket No. CP17-40-000, Comments at 1.

[14] Spire Missouri Oct. 5, 2021 Comments at 7.

[15] Id. at 7 n.15.

[16] See supra note 10.

[17] See, e.g., ANR Pipeline Company et al., Commission Staff Notice of Intent to Prepare an Environmental Impact Statement, Docket Nos. CP20-484-000 and CP20-485-000 (July 7, 2021); Tennessee Gas Pipeline Company, L.L.C., et al., Commission Staff Notice of Intent to Prepare an Environmental Impact Statement, Docket Nos. CP20-50-000 and CP20-51-000 (June 30, 2021); North Baja Pipeline, LLC, Commission Staff Notice of Intent to Prepare an Environmental Impact Statement, Docket No. CP20-27-000 (May 27, 2021); Iroquois Gas Transmission System, L.P., Commission Staff Notice of Intent to Prepare an Environmental Impact Statement, Docket No. CP20-48-000 (May 27, 2021); Tennessee Gas Pipeline Company, L.L.C., Notice of Intent to Prepare an Environmental Impact Statement, Docket No. CP20-493-000 (May 27, 2021); Columbia Gulf Transmission, LLC, Notice of Intent to Prepare an Environmental Impact Statement, Docket No. CP20-527-000 (May 27, 2021); Adelphia Gateway, LLC, Notice of Intent to Prepare an Environmental Impact Statement, Docket No. CP21-14-000 (May 27, 2021); see also N. Nat. Gas Co., 175 FERC ¶ 61,189 (2021) (Danly, Comm’r, concurring in part and dissenting in part at P 1) (discussing the “new ‘standard’—referred to (by some) as the ‘eyeball’ test—for determining the significance of a project’s emissions” set forth in Northern Natural Gas Company, 174 FERC ¶ 61,189 (2021)); Algonquin Gas Transmission, LLC, 174 FERC ¶ 61,126 (2021) (reopening the Atlantic Bridge Project certificate order).

[18] See Miranda Wilson, FERC meeting: Pipelines, blackouts and ‘fearmongering,’ EnergyWire, Nov. 19, 2021 (“Although FERC did not take action yesterday to extend the company’s temporary certificate, Glick said it was his ‘intent’ for the commission to act on Spire’s application before Dec. 13.”).

Contact Information


This page was last updated on December 16, 2021