Commissioner James Danly Statement
December 16, 2022
Project No. 1333-066

I concur with the finding that Tule Hydro LLC is qualified to be the licensee for the Tule River Hydroelectric Project.[1]  As in other recent license transfer orders,[2] I dissent in part because the majority violates the Federal Power Act by amending the license to reserve the Commission’s authority to impose financial assurance mechanisms in a transfer proceeding.[3]

For these reasons, I respectfully concur in part and dissent in part.

 

 

[1] See Pac. Gas & Elec. Co., 181 FERC ¶ 61,231 (2022).

[2] See, e.g., Rivers Elec. Co., Inc., 178 FERC ¶ 61,027 (2022) (Danly, Comm’r, concurring in part and dissenting in part).

[3] See Pac. Gas & Elec. Co., 181 FERC ¶ 61,231 at P 7.

Contact Information


This page was last updated on December 16, 2022